May 2024 – Network Performance Summary
Local Authority Area (Not Owner*) | Tickets Raised | Power Drawn (kWh) | Sessions | Total Number of chargers per area | Uptime % (Overall for month 97.98%) |
Aberdeen City | 44 | 61,753 | 3087 | 76 | 93.65% |
Aberdeenshire | 73 | 61,988 | 2976 | 97 | 98.65% |
Angus | 24 | 50,933 | 2623 | 63 | 98.65% |
Argyll and Bute | 88 | 68,902 | 3353 | 75 | 99.70% |
City of Edinburgh | 123 | 172,398 | 10816 | 196 | 94.07% |
Clackmannanshire | 5 | 13,520 | 614 | 40 | 93.15% |
Dumfries and Galloway | 61 | 54,058 | 2375 | 210 | 96.50% |
Dundee City | 35 | 160,451 | 8085 | 112 | 96.02% |
East Ayrshire | 59 | 112,691 | 4770 | 74 | 99.15% |
East Dunbartonshire | 14 | 17,841 | 1350 | 21 | 96.25% |
East Lothian | 37 | 66,086 | 3173 | 106 | 99.73% |
East Renfrewshire | 8 | 21,973 | 1095 | 22 | 98.19% |
Falkirk | 33 | 70,269 | 3168 | 99 | 98.63% |
Fife | 99 | 183,743 | 7077 | 105 | 96.24% |
Glasgow City | 90 | 159,119 | 8065 | 219 | 97.47% |
Highland | 188 | 174,210 | 8558 | 228 | 90.47% |
Inverclyde | 5 | 11,341 | 717 | 29 | 93.83% |
Midlothian | 13 | 34,356 | 1763 | 57 | 94.00% |
Moray | 41 | 39,592 | 1925 | 41 | 97.58% |
Na h-Eileanan an Iar | 29 | 20,464 | 954 | 49 | 95.10% |
North Ayrshire | 38 | 72,642 | 3220 | 58 | 86.92% |
North Lanarkshire | 91 | 97,717 | 4629 | 156 | 99.18% |
Orkney Islands | 11 | 13,824 | 875 | 34 | 98.89% |
Perth and Kinross | 70 | 108,995 | 5516 | 95 | 85.23% |
Renfrewshire | 34 | 81,020 | 4143 | 87 | 95.68% |
Scottish Borders | 49 | 47,709 | 2655 | 50 | 97.45% |
Shetland Islands | 16 | 12,657 | 590 | 33 | 99.68% |
South Ayrshire | 54 | 65,816 | 2653 | 43 | 83.09% |
South Lanarkshire | 62 | 106,582 | 4859 | 170 | 96.81% |
Stirling | 70 | 94,336 | 4670 | 125 | 98.92% |
West Dunbartonshire | 19 | 34,180 | 1664 | 30 | 98.43% |
West Lothian | 24 | 45,605 | 2327 | 58 | 91.21% |
Local Authority Area: This has been categorised by region; however, this is not necessarily the owner of the charge point, this is just where the charger is located.
Tickets / Month: The total number of any issue, query or fault raised in the month specific to the charger. This could include- tariff query, RFID request, remote activation assistance, how-to advice, user error, machine fault.
Power Drawn (kWh): The total number of kWh drawn from all the charge point sessions in that local authority area.
Sessions: The number of charging sessions per LA area per month.
Total Number of Chargers per Area: The total number of charging points available in the LA area, owned by the LA, other public bodies, charities and businesses.
Uptime %: System calculation of cumulative “unavailable” periods versus potential monthly availability.